What should be checked before commissioning a fixed detector?

Confirm the model, target gas, range, certificate, location, mounting, cable glands, grounding, supply voltage, polarity, loop resistance, output scaling, controller configuration, and alarm logic. Remove transport or sensor protection only as instructed. Complete zero and span work, functional tests, and system interlock tests before handover.